The electric power distribution system plays a critical role in delivering electrical energy from sub-stations to final consumers. Voltage quality is a key indicator of distribution system reliability, as unstable voltage can cause equipment malfunctions and reduce customer satisfaction. Voltage drop often occurs in distribution feeders due to line length, high load, and conductor characteristics. This condition is also identified in the TC-11 Express Feeder at the Pulo Tiga Switchyard, supplied by the Tualang Cut Sub-station under PT PLN (Persero) UP3 Langsa, where a decline in voltage quality has been observed at several network points. This study aims to analyze the voltage profile, identify the primary factors causing voltage drop, and determine the most effective improvement methods to enhance voltage quality. The research methodology adopts a descriptive-analytical approach combined with quantitative analysis using technical network data, including load current, line impedance, and feeder length. The standard references utilized are SPLN D3.002-1: 2012 guidelines. Technical improvement methods evaluated in this study are network reconfiguration, capacitor bank installation, and transformer tap changer adjustment. The results of this study are expected to provide an objective technical reference for PLN in optimizing voltage profiles and ensuring sustainable electricity service quality.

Downloads

Download data is not yet available.

References

Ahmad Hermawan, Ahmad Koimam, Rhezal Agung Ananto, & Satria Luthfi Hermawan. (2024). Evaluasi Ketidakseimbangan Beban Pada Penyulang Unicora. Elposys: Jurnal Sistem Kelistrikan, 11(2), 104–109. https://doi.org/10.33795/elposys.v11i2.5191

Alfaoqi, M. (2024). Singkronisasi Penyulang Incoming Gh Terban Untuk Peningkatan Kehandalan Dan Perbaikan Susut Teknik Pada Pt. Pln (Persero) Ulp Kuala Simpang. Power Elektronik : Jurnal Orang Elektro, 13(2), 219–224. https://doi.org/10.30591/polektro.v13i2.6701

Arifyanto, D. (2023). Analisis Penentuan Letak Trafo Distribusi Pada Penyulang Walmas Menggunakan ETAP Power Station 12.6.0. Jurnal Teknologi Elekterika, 20(1), 57. https://doi.org/10.31963/elekterika.v20i1.4502

Ashari, A., Widiantoro, A., & Mahardika, E. (2018). Sistem Penempatan Transformator Distribusi. Cyclotron, 1(2), 16.

Devitria, Rosa, Wulandari, R., & Elfia, M. (2019). Vol. 1 No.4 Edisi 2 Juli 2019 http://jurnal.ensiklopediaku.org Ensiklopedia of Journal. Jurnal EMBA, 1(4), 153–157.

Dwi Mediansyah. (2015). Politeknik Negeri Sriwijaya Palembang. Rancang Bangun Mesin Pemotong Dan Pembentuk Batu Akik (Perawatan Dan Perbaikan), (2006), 6–17.

Hardiantono, D., Letsoin, Y., & Sumbung, F. H. (2020). SIMULASI PERBAIKAN KUALITAS TEGANGAN PADA JARINGAN DISTRIBUSI MENGGUNAKAN ELECTRICAL TRANSIENT ANALYSIS PROGRAM Abstrak Kontinuitas penyaluran daya listrik pada jaringan distribusi salah satunya ditentukan oleh baik tidaknya kualitas tegangan dalam jaring. Mustek Anim Ha, 9(2), 49–55.

Haris Sasmita, D. P., Hermawan, H., & Handoko, S. (2020). ANALISIS RUGI – RUGI DAYA DAN JATUH TEGANGAN UNTUK REKONFIGURASI PENYULANG RWO 05 DAN RWO 07 GARDU INDUK RAWALO MENGGUNAKAN ETAP 12.6 DAN MATLAB R2018a. Transient: Jurnal Ilmiah Teknik Elektro, 9(4), 480–489. https://doi.org/10.14710/transient.v9i4.480-489

Hasibuan, A., Asran, A., Adriansyah, F., Ismail, B., Siregar, W. V., & Sayuti, M. (2023). Planning to Reconfigure the 150 kV Transmission Network at PT. PLN (Persero) Tualang Cut Network and Substation. Journal of Renewable Energy, Electrical, and Computer Engineering, 3(2), 61–68. https://doi.org/10.29103/jreece.v3i2.11740

Jhonson, S. M., Thamrin, S., & Johannes, S. (2020). Analisis Peningkatan Kinerja Jaringan Distribusi 20Kv Dengan Metode Thermovisi Jaringan Pt. Pln (Persero) Ulp Medan Baru. Jurnal Teknologi Energi Uda, 9(1), 9–10. https://api.semanticscholar.org/CorpusID:225552310

June, V. N., Aji, A. P., Irawan, D., Astutik, R. P., Elektro, T., Teknik, F., Gresik, U. M., No, J. S., Malang, G., Kebomas, K., & Gresik, K. (2025). Analisis Pemasangan Kapasitor Bank sebagai Solusi untuk Mengurangi Drop Tegangan pada Penyulang Lowayu aliran daya pada penyulang LOWAYU , karena metode ini dapat menyelesaikan anlisa ialah dengan penambahan kapasitas pada trafo distribusi , sinkronisasi sistem distribusi Transient Analisis Program ) Power Station , yang di gunakan sebagai sarana untuk. 3(June), 1–31.

Lee, H. O., Kim, D. J., Kim, C. S., & Kim, B. (2023). Optimal Voltage Control Method for a Step Voltage Regulator Considering the Under-Load Tap Changer in a Distribution System Interconnected with a Renewable Energy Source. Energies, 16(16). https://doi.org/10.3390/en16166039

Lim, H., Jo, J., & Chun, K. H. (2025). Optimal On-Load Tap Changer Tap Control Method for Voltage Compliance Rate Improvement in Distribution Systems, Based on Field Measurement Data. Energies, 18(2), 1–16. https://doi.org/10.3390/en18020439

Penyulang, P., Pt, A., Rayon, P. L. N., Palembang, R., & Marniati, Y. (2022). Analisis Penambahan Jurusan Gardu Distribusi I . 598. 19.

Prasetyo, B. (2025). Analisis Rugi-Rugi Daya dan Jatuh Tegangan pada Sistem Distribusi di PT PLN (Persero) ULP Bengkalis Segmen Penyulang Banten RC Meskom Menggunakan …. 7(2), 96–106. https://eprints.polbeng.ac.id/id/eprint/2986/%0Ahttps://eprints.polbeng.ac.id/id/eprint/2986/2/2.TA-3204211412-Bab I Pendahuluan.pdf

Rizkiana, A. F., & Saputra, Y. M. (2024). Perbaikan Jatuh Tegangan dan Rugi Daya dengan Rekonfigurasi Jaringan Sambungan Rumah dan Rekonduktor Jaringan Tegangan Rendah pada Gardu Distribusi MI-44-150-21 PT PLN ULP Magelang Kota. Jurnal Listrik, Instrumentasi, Dan Elektronika Terapan, 5(1), 1. https://doi.org/10.22146/juliet.v5i1.87020

Saleem, S. A., Rama Rao, J. V. G., & Lokeshwar Reddy, C. (2024). Rehabilitation and Techno design of Distribution transformer and 11kV feeder of a radial distribution system. E3S Web of Conferences, 472. https://doi.org/10.1051/e3sconf/202447201019

Saputri, N., Bakhtiar, B., & Asri, A. (2023). Perancangan Pemasangan Express Feeder Untuk Perbaikan Profil Tegangan Pada Jaringan Distribusi 20 kV Penyulang Gardu Hubung Sungguminasa (GHSM) PT …. Seminar Nasional Teknik Elektro …, 376–380. http://jurnal.poliupg.ac.id/index.php/sntei/article/view/3576%0Ahttp://jurnal.poliupg.ac.id/index.php/sntei/article/download/3576/3548

Suseno, A., Adyatma, S., Jaya, A., Nawir, M., & Amin, M. (2025). Analisa Uprating JTM 20 kV di Penyulang Tolandona Out Labunia Untuk Perbaikan Tegangan Pelanggan PT. KPA dan Sekitarnya. Jurnal LOGITECH Logika Technology, 8(2), 129–140. https://doi.org/10.64109/178yb896

Tana, N. M., Likadja, F., & Galla, W. F. (2019). Rekonfigurasi Jaringan Pada Saluran Udara Tegangan Menengah 20 Kv Penyulang Naioni Pt. Pln (Persero) Ulp Kupang Menggunakan Perangkat Lunak Electrical Transient Analysis Program (Etap) 12.6. Jurnal Media Elektro, VIII(1), 41–52. https://doi.org/10.35508/jme.v8i1.1441

Wijanarko, R. F., & Utami, A. R. (2024). Peningkatan Performance Index Tegangan Melalui Pemasangan Kapasitor Bank Pada Gardu Induk Distribusi 20 Kv : Study Case Gardu Induk Betung. El Sains: Jurnal Elektro, 6(1), 9–14. https://doi.org/10.30996/elsains.v6i1.10886

Yahya, Muliadi, dan S. (2024). Perhitungan Jatuh Tegangan Pada Gardu Distribusi ULP Kota Fajar Aceh Selatan. 4, 4–8.

Yahya Sunardi, A., & Mustaghfiri, dan. (2022). Analisisis Sistem Proteksi Jaringan Tegangan Menengah 20 Kv Rsup Dr. Kariadi Semarang. Transient, 10(3), 2685–0206. https://ejournal3.undip.ac.id/index.php/transient

Zuraidah, T., AmaniDarma, T., Siti, A., & Tri, Y. K. (2020). Penggunaan Kapasitor Bank Sebagai Solusi Drop Tegangan Pada Jaringan 20 kV. Semnastek Usu, 82–86.

Downloads

Published

2026-04-30

How to Cite

Azman Yusliansyah, Zuraidah Tharo, & Adi Sastra Pengalaman Tarigan. (2026). Analisis Perbaikan Tegangan Penyulang TC-11 Express Gardu Hubung Pulo Tiga dari GI Tualang Cut di PT PLN UP3 Langsa. Jurnal Teknik Informatika Dan Teknologi Informasi, 6(1), 683–693. https://doi.org/10.55606/jutiti.v6i1.7880

Similar Articles

1 2 3 4 5 6 7 8 9 10 > >> 

You may also start an advanced similarity search for this article.